Carl A. Nelson and Company, provided a tour and update on the new 5/6 building which is scheduled to open in the fall of 2023.
On March 3, 2020, voters in the College Community School District approved a $54M bond referendum to construct a new 5/6 building on 80 acres directly south of Prairie Point. Funds generated from the bond referendum in conjunction with SAVE dollars also include significant renovations to our current Prairie Creek building in preparation for our 9th graders and district programs.
Below is a construction update for November 4, 2021.
- 93% Foundation Work Completed
- 30% Masonry Completed
- 80% Underground Plumbing Completed
- 90% Underground Utilities Completed
- Majority of Earth Work Completed
- Geothermal Work Continues
Priorities over the next few months is erecting pre-cast floors, walls, steel and masonry.

Activities Entrance

Band Room

Classroom Neighborhood

Cafeteria Serving Area

Gym Area