Progress continues on the new 5/6 building which is located south of Prairie Point Middle School. Below is a Spring 2023 Construction Update on the new 5/6 building which is scheduled to open in the fall of 2023. On March 3, 2020, voters in the College Community School District approved a $54M bond referendum to construct a new 5/6 building on 80 acres directly south of Prairie Point. Funds generated from the bond referendum in conjunction with SAVE dollars also include significant renovations to our current Prairie Creek building in preparation for our 9th graders and district programs.
AREA A: Administrative, Art, Music, Special Education
AREA B: Cafeteria, Classrooms, Multipurpose Room, Media Center
AREA C: Classrooms
Work Status Through March 17, 2023
● Wood gym floor installed; Finishing and painting of floor in progress
● Terrazzo Flooring at lunch and serving area complete
● Epoxy kitchen floor complete
● Sound Ceiling in music rooms complete
● 50% of Carpet installed in Area B & C Neighborhoods
● 90% of acoustical ceiling grid and ceiling tile installed on job
● 90% of wood casework installed on job
● 90% of plumbing fixture installed on job
● 90% of light fixture installed on job
● Install if ACM panels (aluminum composite material) at building exterior ongoing
● All HVAC Equipment to be tested and started up by end of March
● Installation of interior doors and hardware has started in neighborhoods
Coming in the Next Few Months
● Installation of flooring in Area A and Area B Center
● Continue Installation of doors and hardware
● Installation of exterior site and building lighting
● Installation of playground equipment
● Placement of concrete sidewalks around the building