Progress continues on the new 5/6 building which is located south of Prairie Point Middle School. Below is a Winter 2023 Construction Update on the new 5/6 building which is scheduled to open in the fall of 2023.

Work Status Through January 5

  • All gym equipment Installed
  • All acoustical ceiling grid installed in classroom neighborhoods
  • All wood casework installed in classroom neighborhoods
  • Elevator installed
  • All lighting and HVAC grilles and diffusers installed in classroom neighborhoods
  • Rubber sheet flooring installation started in classroom neighborhoods
  • Locker installation is ongoing in classroom neighborhoods
  • Drywall finishing and painting ongoing at lunch area/multipurpose room and media center


Coming up in the Next Few of Months

  • Installation of sound ceiling in music classrooms
  • Wood casework installation to begin in art and music classrooms
  • Carpet installation to begin in Area B classroom neighborhood
  • Install ACM panels (aluminum composite material) at building exterior
  • Installation of plumbing fixtures in classroom neighbors
  • Startup of HVAC equipment in Area A
  • Terrazzo flooring installation at lunch area/multipurpose room