2d0f2bf5 c7fb 4f22 8f6b 20c688999306

Big changes are taking place at the Prairie Summit YMCA project — though not all of them are visible from the road these days. The most notable exterior progress includes the asphalt parking lot and road extensions, which are nearing completion along with the installation of parking lot light poles.

Inside, the Myrtha recreation pool structure is nearly complete, and the final concrete slabs have been poured to allow Myrtha crews to begin assembling the competition pool next week.

Throughout the rest of the building, crews are busy installing overhead mechanical, electrical, plumbing, and fire suppression systems. Curtain wall framing is also being set around the exterior, helping to close in the building before winter weather arrives.

Click here to learn more about the Prairie Summit YMCA project.

0aade0a6 57dd 4a05 8c33 dcd227a0102b
0177670b cc55 48b1 a626 a38e1e986bb6
E6980b04 dbfc 43bf 81fd d2d1cd2522a2