DCIM101MEDIADJI 0748.JPG

Progress continues on the new 5/6 building which is located south of Prairie Point Middle School. Below is a Fall 2022 Construction Update on the new 5/6 building which is scheduled to open in the fall of 2023.

Fall 2022 Construction Update

  • Site work complete by end of October
  • Concrete curb and gutter compete at roads by the end of October
  • Installation of base coat of asphalt ongoing and will be complete by early November
  • Painting of walls started September and will be ongoing through November
  • Started installation of acoustical ceiling grid in classroom neighborhoods
  • Rough-in of electrical, plumbing and HVAC duct ongoing
  • Installation of bathroom tile at classroom neighborhoods to be completed by the end of October


Coming up in the Next Few of Months

  • Wood casework to begin in classroom neighborhoods
  • Start-up HVAC equipment in classroom neighborhoods
  • Installation of lights in classroom neighborhoods
  • Installation of gym equipment