MultivistaPhoto 2022 04 07

Construction progress continues on the new 5/6 building which is located south of Prairie Point Middle School. Below is an April 2022 update on the new 5/6 building which is scheduled to open in the fall of 2023.

Below is an April 2022 construction update:

Area A: Administrative, Art, Music, Special Education
Area B: Cafeteria, Classrooms, Multipurpose Room, Media Center
Area C: Classrooms

  • Area A & B: Joists and Deck Complete
  • Area C: Upper Level Masonry: 90% complete with structural block
  • Area C Lower Level: Slab on Grade in Classroom Areas Complete
  • Area C Lower Level: Electrical Rough-in
  • Area A & B Neighborhoods Lover Level: Fire Sprinkler Piping Rough-in
  • Area B Center Lower Level: Multipurpose Room Concrete Slab Completed

Coming up in the Next Couple of Month: 

  • Windows and Glass
  • Installation of Roofs
  • Installation of Face Brick
  • Geothermal Work

On March 3, 2020, voters in the College Community School District approved a $54M bond referendum to construct a new 5/6 building on 80 acres directly south of Prairie Point.  Funds generated from the bond referendum in conjunction with SAVE dollars also include significant renovations to our current Prairie Creek building in preparation for our 9th graders and district programs.